12 August 2012

How to Build a Straight Form for Concrete

Building a straight form for concrete is fairly simple as long as the correct techniques are used. The depth and width of the concrete placement determine the bracing and forming material required. This article will refer to a slab form, wall forms have completely different requirements.

Steps


  1. Lay out the corner positions of the slab using stakes and string lines. A builder's level is ideal for establishing the grade of the top of concrete, but an inexpensive line level will give decent results on short spans.
  2. Measure diagonally on square and rectangular slabs from corner to corner, shifting parallel sides until the diagonal measurements are equal, while the lengths of the sides remain the desired widths. For simple shapes and small size slabs, this "working line" is sufficient, but for complex shapes and large critical layouts, "batter boards" should be used so that the established building lines will be available to recheck layout as forming progresses.
  3. Place the form board starting at one corner alongside the string line, staking it down about 1/8 inch from the line with sharpened wood stakes. The thickness of the slab will determine the spacing of the stakes, as well as the nominal dimension of the forming lumber. As an example, a 1X4 pine board is usually stiff enough to support a 4 inch concrete placement (pour), where an 8 to 12 inch slab thickness will require 2 inch dimension lumber of a width equal to the height. To insure ease of forming, select straight, flat lumber with minimal knots at the lumberyard.
  4. Stake 4 inch slabs a minimum of 32 inches on center, and deep enough to firmly support the form, depending on the stability of the soil beneath the form. For thicker slabs, decrease your stake spacing, a 12 inch slab will need to be staked no more than 24 inches on center. Nail the forms to the stakes level with and almost touching the string line.
  5. Pack the soil around the stakes to lean the form in or out if needed to align it with the string line, and if it is necessary, place a gauge block to hold the string clear of the form and gauge the form at frequent intervals to assure the form is straight.
  6. Drive another row of stakes behind the form 2 to 3 feet for thicker slabs, and nail a kicker, or 2x4 board from the off set stake to the side of the stake nailed to the form to keep it stable. When placing the concrete, you may want to restring each side to make sure the weight of the concrete hasn't bowed the form, and these stakes can be wedged out to correct any bows.


Tips


  • Check alignment of forms by eyeballing them, that is, bending down so that you can sight down the edge of the form.
  • The straighter the lumber you use to form, the easier it will be to align it.
  • Cut stakes long enough to get a good grip in the soil, and sharpen the ends with a long taper to a keen point to make driving them easier.
  • Use a sledgehammer that fits you. 20 pound sledges are far too heavy for most people, an 8 pound is a common choice, and many people cut the handle down to 30 inches or less for better control.


Warnings


  • The only hazards normally encountered in this type of work are splinters, missed blows with the hammer, and nails flying. In the workplace, safety requirements recommend gloves, long pants, boots, and safety glasses in this operation.


Article provided by wikiHow, a wiki how-to manual. Please edit this article and find author credits at the original wikiHow article on How to Build a Straight Form for Concrete. All content on wikiHow can be shared under a Creative Commons license.

No comments:

Post a Comment